MAYORWatch: What’s Delaying the Makawao Ave. Resurfacing Project?

Mayor Michael Victorino answers weekly questions submitted to his office staff.

Question: I was wondering what the holdup is on the Makawao Avenue resurfacing project. There is a portion that was started and not completed. Also, many thanks for resurfacing Pulehu Road.

Answer: I appreciate your gratitude for our dedicated and hard-working employees in the Department of Public Works. It is often a thankless job where their accomplishments can go unnoticed or underappreciated.

Regarding the status on the Makawao Avenue reconstruction, the portion just east of Pulehu Road has been delayed due to the sidewalk/guardrail redesign. We have the completed redesign and received a price from the contractor.

Prior to completing the construction work, however, we will need to obtain review and approval from the state Department of Transportation and the Federal Highways Administration. We expect the reconstruction work to be completed in the next four to five months, but possibly sooner.

For a list of current and future Public Works projects, click here.

Want to Ask the Mayor? Submit your Maui County related questions to Mayor Michael Victorino by email at [email protected], by phone at 270-7855 or by mail at 200 S. High St., ninth floor, Wailuku 96793. Questions submitted will be considered for inclusion in the “Ask theMayor” column; to request a personal response to a concern, email [email protected]

Comments

comments

Check Also

Hawaiian Practitioner Sam Ka’ai to speak at Farmers Meeting

Hawai’i Farmers Union United’s Mauna Kahalawai Chapter presents an evening with respected Hawaiian practitioner and …